STATE ROAD 500

Location

Orange County/Osceola County line north to Taft-Vineland Road 

Client

Florida Department of Transportation (FDOT) District 5

Project Description

  • Pond design for widening of existing four lanes to six lanes 

Services Provided

  • Pond siting report
  • Final drainage design
  • Coordinate with developers, Orange County, South Florida Water Management District, Expressway Authority, and property owners
  • Permitting  
    • South Florida Water Management District drainage submittal
    • Florida Department of Environmental Protection stormwater submittal

Project Challenges

Coordinate with South Florida Water Management District and Expressway Authority to revise two existing ponds to eliminate the need for a new five acre pond site - savings of approximately $1,000,000 for Florida Department of Transportation

Status

Construction to begin January 2004